Collateral warranties for building design and construction
Contents |
[edit] What is a collateral warranty?
Collateral warranties are agreements that are associated with another 'primary' contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.
For a detailed legal definition of collateral warranties, see: Definition of collateral warranty.
[edit] Why are collateral warranties needed?
They came into being as a result of the courts deciding that defects in buildings were not recoverable in tort, as they were an economic loss which was only recoverable through a contractual relationship. Collateral warranties therefore create direct contractual relationships between parties that would not otherwise exist.
A typical example would be where an architect of a new office development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.
[edit] What terms might a collateral warranty include?
There are a number of standard forms of collateral warranty (such as Joint Contracts Tribunal (JCT) collateral warranties), however there can be some dispute about their specific terms, with clients often claiming that industry standard warranties favour contractors and designers. There can also be difficulties with onerous terms that designers or contractors are unable to agree to as their insurers will not provide cover. As a consequence many collateral warranties are bespoke.
Collateral warranties may include 'step-in' rights allowing the beneficiary to step-into the role of the client. This can be important, for example to banks providing funding for a project, enabling them to ensure that the project is completed if the client becomes insolvent.
There may also be a contractual requirement for parties to obtain further warranties, for example there may be an obligation for the main contractor to obtain parallel collateral warranties from sub-contractors.
One of the disadvantages of collateral warranties is the difficulty in actually completing them. On large projects with many consultants and sub-contractors and multiple occupants, there can be a great number of warranties. The Contracts (Rights of Third Parties) Act can offer a way around this difficulty by allowing the primary contracts to confer benefits upon third parties even though they are not a party to that contract.
See also: Practical considerations of collateral warranties.
[edit] Case law relating to collateral warranties
[edit] Parkwood Leisure Limited v Laing
In the case of Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited in 2013, the judge found that Parkwood’s collateral warranty qualified as a 'construction contract' as the definitions were widely construed and so The Housing Grants, Construction and Regeneration Act applied to it as it covers all contracts related to the carrying out of construction operations.
The Housing Grants, Construction and Regeneration Act 1996 (HGRA - also known as the Construction Act) is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly. The Act applies to all contracts for 'construction operations' (including consultants' appointments). If construction contracts fail to comply with the act, then the Scheme for Construction Contracts applies.
For more information see: Housing Grants, Construction and Regeneration Act
The court’s decision was an unexpected one for practitioners who assumed the Act did not apply to warranties.
For more information see: Parkwood Leisure Limited v Laing.
Collateral warranties will now be subject to greater scrutiny in the light of this case, with resistance from contractors and consultants to grant warranties and a desire to restrict the number and scope of warranties. That inevitably means further complications for the negotiation and drafting of warranties resulting in protracted and costly negotiations.
The upshot of this could now see the rise of third party rights as circumventing the issues surrounding collateral warranties.
For more information see: Rights of third parties.
See also: Difference between collateral warranties and third party rights.
[edit] Other cases
Other examples of case related to collateral warranties include:
- D&F Estates Limited and Others v Church Commissioners for England and others.
- Murphy v Brentwood District Council.
- Squibb Group Ltd v London Pleasure Gardens Ltd & Anor 2013.
- In 2024, the Supreme Court found that collateral warranties do not constitute construction contracts, overturning the 2022 ruling of the Appeal Court in the case of Abbey Healthcare v Simply Construction.
[edit] Related articles on Designing Buildings
- Agency.
- Appointing consultants.
- Collateral.
- Consultant switch.
- Construction contract.
- D&F Estates Limited and Others v Church Commissioners for England and others.
- Defects.
- Definition of collateral warranty.
- Design liability.
- Difference between collateral warranties and third party rights.
- Guarantees.
- Housing Grants, Construction and Regeneration Act.
- Murphy v Brentwood District Council.
- Novation.
- Parkwood Leisure Limited v Laing.
- Parent company guarantee.
- Performance bond.
- Practical considerations of collateral warranties.
- Scheme for Construction Contracts.
- Squibb Group Ltd v London Pleasure Gardens Ltd & Anor 2013.
- Step-in rights.
- Sub contractors.
- The Contracts (Rights of Third Parties) Act.
- Warranty.
[edit] External references
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments
To make a comment about this article, click 'Add a comment' above.
Separate your comments from any existing comments by inserting a horizontal line.
The supply chain is so long now it can be really difficult to get back to back warranties in place.